Site icon Martin City Telegraph

Red Bridge Road ready for construction in December

By 2023, Red Bridge Rd. will be expanded between Wornall and Holmes.

By Kathy Feist

Road construction on the segment of Red Bridge Road between Holmes and Wornall is expected to begin in December, according to Kansas City Public Works.  

The road had been undergoing utility relocations. KCPW reports that AT&T Local, AT&T Transmission, Consolidated, Spire, K-Powernet, Google Fiber, and Zayo have completed utility relocations.  United Private Network, Spectrum, and Evergy are still relocating their facilities. All utilities are expected to be out of the way by November.

 Bids for the roadway project were opened on August 4. The project should be completed by fall 2023 and will include: 

 

Exit mobile version